Aggregate Subgrade and Utility Work Progressing

Work Completed This Week
The contractor completed the proof roll and performed necessary subgrade undercuts throughout the Hook Drive Extension corridor. A pressure test was completed on the east section of the 8-inch ductile iron water main. Excavation for directional drilling across Orchard Lane was completed, and two runs of street lighting conduit were installed across the corridor.

Silt fence was installed along Nicole Lane and Woodbine Lane, and the remaining subgrade excavation at the Hook Drive limits near Orchard Lane and Nicole Lane was completed, with excess material hauled off-site. The contractor also installed the 9-inch PGE aggregate subgrade along approximately 95 percent of the corridor and stabilized slopes with permanent seed and blanket. Storm sewer installation began along Nicole Lane. Placement of the 3-inch capping aggregate was also scheduled to begin Saturday.

Work Anticipated Next Week
Installation of the 3-inch capping aggregate is expected to be completed along the Hook Drive Extension. Roadway pipe underdrains are anticipated to begin, while installation of street lighting conduit is scheduled to continue throughout the corridor. PCC curb and gutter installation is planned to begin along Hook Drive. Storm sewer work along Nicole Lane is projected to continue, and maintenance transfer activities along with installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are expected to take place.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.