Work Completed Last Week The contractor began installing concrete foundations for the permanent traffic signals at the Rollins Road and Nicole Lane/Woodbine Drive intersection. Pavement patches were placed at the Hook Drive and Orchard Lane intersection, and miscellaneous curb and gutter replacements were completed. Frame and lid adjustments within the pavement along Nicole Lane and Woodbine Drive were also completed in preparation for Hot Mix Asphalt surface course placement.
Work Anticipated This Week Concrete foundation installation for the permanent traffic signals at the Rollins Road and Nicole Lane/Woodbine Drive intersection is expected to be completed. Longitudinal joint sealant and tack coat are anticipated to be placed along Hook Drive, Nicole Lane, and Woodbine Drive in preparation for Hot Mix Asphalt surface course paving. Surface course paving is scheduled to follow along all three roadways. Installation of the aggregate base for sidewalks at the intersection corners is also planned.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
The contractor excavated the corners of the Rollins Road and Nicole Lane/Woodbine Drive intersection down to subgrade in preparation for sidewalk and traffic signal improvements.
Work Anticipated This Week
Installation of concrete foundations for the permanent traffic signals at the Rollins Road and Nicole Lane/Woodbine Drive intersection is anticipated. Frame and lid adjustments within the pavement along Nicole Lane and Woodbine Drive are expected to be completed in preparation for Hot Mix Asphalt surface course placement. Installation of the 4-inch aggregate base for sidewalks at the intersection corners is also planned.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor adjusted valve boxes along Woodbine Drive and mortared new drainage structures along Nicole Lane and Woodbine Drive.
Work Anticipated Next Week Excavation of the intersection corners at Rollins Road and Nicole Lane/Woodbine Drive is expected to begin in preparation for permanent traffic signal improvements. Installation of the concrete foundations for the permanent traffic signals is also anticipated at the intersection.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
The contractor installed permanent seed and blanket along Nicole Lane, Woodbine Drive, and Hook Drive, continuing the remaining landscape restoration throughout the project corridor.
Work Anticipated Next Week
Installation of the concrete foundations for the permanent traffic signals at the Rollins Road and Nicole Lane/Woodbine Lane intersection is expected to begin.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
The contractor addressed various sediment and erosion control items throughout the project site. Fine grading of the topsoil also began along the Hook Drive Extension in preparation for final landscape restoration.
Work Anticipated Next Week
Permanent seed and blanket installation is expected to begin along Nicole Lane and Woodbine Drive.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
The contractor completed pavement patching and placed the asphalt leveling binder along Nicole Lane and Woodbine Drive. The final lift of asphalt was also completed for all driveways along both roadways.
Work Anticipated This Week
Installation of permanent seed and blanket along Nicole Lane and Woodbine Drive is expected to begin, weather permitting.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor completed topsoil respread along Nicole Lane and Woodbine Drive. The remaining sidewalk gaps along Hook Drive and the sidewalk along the north end of Nicole Lane were prepared and poured. The Lake County Traffic Court sign was reinstalled along Nicole Lane, and mailboxes along Woodbine Drive were returned to their permanent locations. Milling of Nicole Lane and Woodbine Drive was also scheduled to begin on Saturday.
Work Anticipated Next Week Pavement patching and placement of the asphalt leveling binder along Nicole Lane and Woodbine Drive are expected to be completed. The final lift of asphalt is scheduled to be placed on all driveways along Nicole Lane and Woodbine Drive. Permanent seed and blanket installation is anticipated to begin along Nicole Lane and Woodbine Drive, weather permitting.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor continued topsoil respread along Nicole Lane and Woodbine Drive and completed additional concrete sidewalk placement. Concrete curb and gutter, along with the concrete driveway at the northern Oak Hill entrance from Hook Drive, were poured. The Lake County Courthouse sign was also reinstalled along Nicole Lane.
Directional drilling for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection continued. The contractor prepared and paved Hot Mix Asphalt binder course at the driveways along Nicole Lane and Woodbine Drive. Installation of conduit for the streetlight pole bases was completed, and concrete was poured for all streetlight pole bases and the streetlight foundation along the Hook Drive Extension. Pull tape was also installed through the street lighting conduit in preparation for future cable installation.
Work Anticipated Next Week Topsoil respread along Nicole Lane and Woodbine Drive is expected to continue. Concrete sidewalk placement is anticipated to progress throughout the week. Milling, pavement patching, and placement of the leveling binder course along Nicole Lane and Woodbine Drive are scheduled to be completed.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed Last Week The contractor completed topsoil respread adjacent to the new sidewalk along the Hook Drive Extension. Most of the concrete curb and gutter was poured along Woodbine Drive and Nicole Lane. Directional drilling began for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection, and auguring was completed for the streetlight bases. The contractor also continued grading the aggregate base for roadway widening in preparation for paving and placed the 4-inch Hot Mix Asphalt binder course along the widened sections of Nicole Lane and Woodbine Drive.
The Nicole Lane road closure and detour were removed, and the roadway reopened to traffic early Friday morning, July 3.
Work Anticipated This Week Final grading behind the new curb and gutter is expected to begin, along with placement of topsoil along Nicole Lane and Woodbine Drive. Small sections of concrete curb and gutter along Woodbine Drive, as well as sidewalk along the north side of Nicole Lane and the east Oak Hill driveway apron, are scheduled to be poured. Completion of the remaining concrete light pole bases for the streetlights is anticipated.
Hot Mix Asphalt binder course paving for the driveways is planned to take place, and seed and blanket installation along Nicole Lane and Woodbine Drive is projected to begin. Installation of the permanent traffic signals at the Rollins Road and Nicole Lane/Woodbine Drive intersection is expected to continue.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor implemented the two-week road closure and detour along Nicole Lane on Monday, June 22. The remaining storm sewer installation on Nicole Lane at Rollins Road was completed, while curb and gutter removal, roadway widening, pipe underdrain installation, and aggregate subbase placement continued along Nicole Lane and Woodbine Drive.
Concrete sidewalk construction progressed along the Hook Drive Extension, with additional curb and gutter poured along Nicole Lane and two driveway aprons completed. The contractor also removed the existing handholes and concrete traffic signal bases at the Rollins Road and Nicole Lane/Woodbine Drive intersection and began installing concrete light pole bases for the proposed street lighting.
Work Anticipated Next Week Directional drilling for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection is expected to begin. Grading of the aggregate base for roadway widening along Nicole Lane and Woodbine Drive is scheduled to continue in preparation for paving. Completion of curb and gutter placement along Nicole Lane and Woodbine Drive is anticipated, along with the remaining concrete light pole bases.
Pavement patching and Hot Mix Asphalt binder course paving are projected to begin in the widened areas of Nicole Lane and Woodbine Drive, with binder course paving for driveways also planned. Topsoil respread adjacent to the new sidewalk along the Hook Drive Extension is expected to be completed. The Nicole Lane road closure and detour signage are anticipated to be removed on Friday, July 3.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.