Work Completed This Week The contractor installed joint sealant along the first lift of Hot Mix Asphalt binder course and finished binder course paving along the Hook Drive Extension. Both detention basins were dewatered due to weekend rain, then fine graded in preparation for final restoration. Stabilization of the basins also began.
The contractor completed a water main adjustment along Woodbine Drive, installed storm sewer along Woodbine Drive, directionally drilled street lighting conduit beneath Orchard Lane, and plowed street lighting conduit along the Hook Drive Extension.
Work Anticipated Next Week Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are anticipated to take place. Storm sewer installation along Woodbine Drive is scheduled to continue. Stabilization of the detention basins is expected to be completed, and street lighting conduit plowing is planned to continue along the Hook Drive Extension. Excavation and grading for the proposed sidewalk are anticipated to begin along the corridor.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor installed inlet filter baskets within the curb along the Hook Drive Extension and continued storm sewer installation along Nicole Lane. Backfilling behind the newly installed curb and gutter progressed throughout the corridor, and the aggregate subgrade was fine graded in preparation for Hot Mix Asphalt binder course paving.
The contractor also connected street lighting conduit above ground in preparation for conduit plowing operations. Both detention basins were dewatered, prime coat was applied, and paving of the Hot Mix Asphalt binder course began along the Hook Drive Extension. Storm sewer installation also began along Woodbine Drive.
Work Anticipated Next Week Placement of longitudinal joint sealant is expected along the first lift of Hot Mix Asphalt binder course. Tack coat application and additional binder course paving are anticipated to continue throughout the corridor. Fine grading of the detention basins with topsoil is planned, and stabilization work within the basins is projected to be completed. Conduit plowing for the proposed street lighting is scheduled to begin. Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are also anticipated to take place.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor installed the capping aggregate along the Hook Drive Extension and completed installation of roadway pipe underdrains throughout the corridor. All storm sewer frames located within the curb and gutter sections were installed, and PCC curb and gutter placement was completed along the extension.
Work Anticipated Next Week Backfilling behind the newly installed curb and gutter is planned to begin along the Hook Drive Extension. Fine grading of the aggregate subgrade is expected to take place in preparation for Hot Mix Asphalt binder course paving. Storm sewer installation along Nicole Lane is anticipated to continue, and Hot Mix Asphalt binder course paving is scheduled to begin along the corridor. Stabilization work within the detention basins is also planned to continue. Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are anticipated to take place.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor completed the proof roll and performed necessary subgrade undercuts throughout the Hook Drive Extension corridor. A pressure test was completed on the east section of the 8-inch ductile iron water main. Excavation for directional drilling across Orchard Lane was completed, and two runs of street lighting conduit were installed across the corridor.
Silt fence was installed along Nicole Lane and Woodbine Lane, and the remaining subgrade excavation at the Hook Drive limits near Orchard Lane and Nicole Lane was completed, with excess material hauled off-site. The contractor also installed the 9-inch PGE aggregate subgrade along approximately 95 percent of the corridor and stabilized slopes with permanent seed and blanket. Storm sewer installation began along Nicole Lane. Placement of the 3-inch capping aggregate was also scheduled to begin Saturday.
Work Anticipated Next Week Installation of the 3-inch capping aggregate is expected to be completed along the Hook Drive Extension. Roadway pipe underdrains are anticipated to begin, while installation of street lighting conduit is scheduled to continue throughout the corridor. PCC curb and gutter installation is planned to begin along Hook Drive. Storm sewer work along Nicole Lane is projected to continue, and maintenance transfer activities along with installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are expected to take place.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor completed the water main tap into the existing system along Orchard Lane and installed the remaining 8-inch ductile iron water main in that area. A temporary asphalt patch was placed over the trench.
Work Anticipated Next Week Drying and compaction of the subgrade are expected to continue along the Hook Drive Extension in preparation for proof rolling. Remaining subgrade excavation at the limits near Orchard Lane and Nicole Lane is scheduled to be completed. Installation of conduit and street lighting foundations is planned to begin, along with roadway pipe underdrains and placement of aggregate subgrade. Installation of silt fence along Nicole Lane and Woodbine Lane is anticipated, and storm sewer installation is expected to begin along Nicole Lane.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor continued earth excavation for the proposed roadway subgrade and final grading throughout the Hook Drive Extension. Excess material was hauled off-site, and placement of topsoil progressed along the slopes on the west half of the corridor.
Work Anticipated Next Week Earth excavation for the proposed roadway subgrade and final grading are expected to be completed throughout the Hook Drive Extension. Installation of electrical conduit for proposed street lighting is scheduled to begin. Roadway pipe underdrain and 12-inch aggregate subgrade are anticipated to be installed along the corridor. The contractor is expected to complete the hot tap into the existing water main along Orchard Lane.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor continued earth excavation for the proposed roadway subgrade throughout the Hook Drive Extension. Work activities were limited due to weather conditions.
Work Anticipated Next Week Earth excavation for the proposed roadway subgrade is expected to continue. Placement of topsoil on the remaining slopes along the west half of the corridor is scheduled to be completed. Installation of roadway pipe underdrain and aggregate subgrade is anticipated to begin. The contractor is scheduled to complete the hot tap into the existing water main along Orchard Lane.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor continued earth excavation for the proposed roadway subgrade throughout the Hook Drive Extension. Placement of topsoil was completed on parkway slopes along the east half of the corridor. The remaining topsoil stockpile was also moved outside of the roadway pavement limits.
Work Anticipated Next Week Earth excavation for the proposed roadway subgrade is expected to continue throughout the Hook Drive Extension. Placement of topsoil is scheduled to be completed on the remaining slopes along the west half of the corridor.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor installed temporary perforated risers and manhole restrictor plates at both basin outfalls. Riprap was placed along the Hook Drive Extension, and excess excavation spoils were hauled off-site. Testing of the installed sanitary sewer and water main was also completed.
Work Anticipated Next Week Hauling of underground excavation spoils and grading of the Hook Drive Extension to subgrade are expected to continue throughout the site. Respreading of topsoil on slopes along Hook Drive is planned to begin.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week Storm sewer installation continued along the south side of the Hook Drive Extension. The contractor also continued installing water main, with fire hydrants placed along the alignment. Excavation and shaping of slopes progressed throughout the corridor.
Work Anticipated Next Week Storm sewer installation is expected to be completed along the Hook Drive Extension. Hauling of spoils and grading to subgrade is scheduled to continue across the site. Topsoild respreading is anticipated to begin along the corridor.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.