Sidewalk Construction Completed and Final Paving Ahead

Work Completed This Week
The contractor completed topsoil respread along Nicole Lane and Woodbine Drive. The remaining sidewalk gaps along Hook Drive and the sidewalk along the north end of Nicole Lane were prepared and poured. The Lake County Traffic Court sign was reinstalled along Nicole Lane, and mailboxes along Woodbine Drive were returned to their permanent locations. Milling of Nicole Lane and Woodbine Drive was also scheduled to begin on Saturday.

Work Anticipated Next Week
Pavement patching and placement of the asphalt leveling binder along Nicole Lane and Woodbine Drive are expected to be completed. The final lift of asphalt is scheduled to be placed on all driveways along Nicole Lane and Woodbine Drive. Permanent seed and blanket installation is anticipated to begin along Nicole Lane and Woodbine Drive, weather permitting.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Sidewalk and Roadway Finishing Work Continuing

Work Completed This Week
The contractor continued topsoil respread along Nicole Lane and Woodbine Drive and completed additional concrete sidewalk placement. Concrete curb and gutter, along with the concrete driveway at the northern Oak Hill entrance from Hook Drive, were poured. The Lake County Courthouse sign was also reinstalled along Nicole Lane.

Directional drilling for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection continued. The contractor prepared and paved Hot Mix Asphalt binder course at the driveways along Nicole Lane and Woodbine Drive. Installation of conduit for the streetlight pole bases was completed, and concrete was poured for all streetlight pole bases and the streetlight foundation along the Hook Drive Extension. Pull tape was also installed through the street lighting conduit in preparation for future cable installation.

Work Anticipated Next Week
Topsoil respread along Nicole Lane and Woodbine Drive is expected to continue. Concrete sidewalk placement is anticipated to progress throughout the week. Milling, pavement patching, and placement of the leveling binder course along Nicole Lane and Woodbine Drive are scheduled to be completed.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Nicole Lane Reopens as Roadway Improvements Continue

Work Completed Last Week
The contractor completed topsoil respread adjacent to the new sidewalk along the Hook Drive Extension. Most of the concrete curb and gutter was poured along Woodbine Drive and Nicole Lane. Directional drilling began for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection, and auguring was completed for the streetlight bases. The contractor also continued grading the aggregate base for roadway widening in preparation for paving and placed the 4-inch Hot Mix Asphalt binder course along the widened sections of Nicole Lane and Woodbine Drive.

The Nicole Lane road closure and detour were removed, and the roadway reopened to traffic early Friday morning, July 3.

Work Anticipated This Week
Final grading behind the new curb and gutter is expected to begin, along with placement of topsoil along Nicole Lane and Woodbine Drive. Small sections of concrete curb and gutter along Woodbine Drive, as well as sidewalk along the north side of Nicole Lane and the east Oak Hill driveway apron, are scheduled to be poured. Completion of the remaining concrete light pole bases for the streetlights is anticipated.

Hot Mix Asphalt binder course paving for the driveways is planned to take place, and seed and blanket installation along Nicole Lane and Woodbine Drive is projected to begin. Installation of the permanent traffic signals at the Rollins Road and Nicole Lane/Woodbine Drive intersection is expected to continue.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Nicole Lane Improvements and Intersection Work

Work Completed This Week
The contractor implemented the two-week road closure and detour along Nicole Lane on Monday, June 22. The remaining storm sewer installation on Nicole Lane at Rollins Road was completed, while curb and gutter removal, roadway widening, pipe underdrain installation, and aggregate subbase placement continued along Nicole Lane and Woodbine Drive.

Concrete sidewalk construction progressed along the Hook Drive Extension, with additional curb and gutter poured along Nicole Lane and two driveway aprons completed. The contractor also removed the existing handholes and concrete traffic signal bases at the Rollins Road and Nicole Lane/Woodbine Drive intersection and began installing concrete light pole bases for the proposed street lighting.

Work Anticipated Next Week
Directional drilling for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection is expected to begin. Grading of the aggregate base for roadway widening along Nicole Lane and Woodbine Drive is scheduled to continue in preparation for paving. Completion of curb and gutter placement along Nicole Lane and Woodbine Drive is anticipated, along with the remaining concrete light pole bases.

Pavement patching and Hot Mix Asphalt binder course paving are projected to begin in the widened areas of Nicole Lane and Woodbine Drive, with binder course paving for driveways also planned. Topsoil respread adjacent to the new sidewalk along the Hook Drive Extension is expected to be completed. The Nicole Lane road closure and detour signage are anticipated to be removed on Friday, July 3.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Nicole Lane Improvements and Sidewalk Construction

Work Completed This Week
The contractor completed storm sewer installation along Woodbine Drive and continued removal of curb and gutter along Nicole Lane. Excavation for roadway widening also progressed, along with installation of pipe underdrain and aggregate subbase.

Most of the concrete sidewalk along the Hook Drive Extension was formed and poured during the week. The contractor also removed the existing south entrance to the Lake County Courthouse on Nicole Lane and excavated for the new entrance and parking stalls. As part of the temporary traffic signal work, the Lake County Division of Transportation interconnect along Rollins Road was rerouted.

Work Anticipated Next Week
A two-week road closure along Nicole Lane is expected to begin Monday morning. Removal of curb and gutter is anticipated to continue along Nicole Lane and Woodbine Drive. Excavation for roadway widening, along with installation of pipe underdrain and aggregate subbase, is scheduled to continue in both locations.

Completion of the remaining storm sewer installation on Nicole Lane at Rollins Road is planned. Forming and pouring of the remaining sidewalk sections along the Hook Drive Extension are expected to continue. Installation of concrete light pole bases is anticipated to begin, and curb and gutter placement along Nicole Lane and Woodbine Drive is planned.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Sidewalk Preparation and Signal Work

Work Completed Last Week
The contractor completed stabilization of both detention basins and continued storm sewer installation along Woodbine Drive. Installation of street lighting conduit along the Hook Drive Extension was completed. The maintenance transfer of the traffic signal at Rollins Road and Nicole Lane/Woodbine Lane was also completed, and installation of temporary traffic signals is underway.

The contractor excavated and graded the proposed sidewalk along the north side of the Hook Drive Extension to subgrade and installed and graded the aggregate base for the future concrete sidewalk.

Work Anticipated This Week
Excavation and grading for the proposed sidewalk along the south side of the Hook Drive Extension are expected to begin, along with installation and grading of the aggregate base. Forming for the concrete sidewalk is anticipated to start along the corridor. Installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane is scheduled to continue.

Removal of curb and excavation for roadway widening along Nicole Lane are planned to begin. Installation of concrete light pole bases along the Hook Drive Extension is anticipated, and removal of transite storm sewer along Woodbine Drive is projected to take place.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Sidewalk Preparation and Signal Work Progressing

Work Completed This Week
The contractor completed stabilization of both detention basins and continued storm sewer installation along Woodbine Drive. Installation of street lighting conduit along the Hook Drive Extension was completed. The maintenance transfer of the traffic signal at Rollins Road and Nicole Lane/Woodbine Lane was also completed, and installation of temporary traffic signals is underway.

The contractor excavated and graded the proposed sidewalk along the north side of the Hook Drive Extension to subgrade and installed and graded the aggregate base for the future concrete sidewalk.

Work Anticipated Next Week
Excavation and grading for the proposed sidewalk along the south side of the Hook Drive Extension are expected to begin, along with installation and grading of the aggregate base. Forming for the concrete sidewalk is anticipated to start along the corridor. Installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane is scheduled to continue.

Removal of curb and excavation for roadway widening along Nicole Lane are planned to begin. Installation of concrete light pole bases along the Hook Drive Extension is anticipated, and removal of transite storm sewer along Woodbine Drive is planned to take place.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Binder Course Paving Completed

Work Completed This Week
The contractor installed joint sealant along the first lift of Hot Mix Asphalt binder course and finished binder course paving along the Hook Drive Extension. Both detention basins were dewatered due to weekend rain, then fine graded in preparation for final restoration. Stabilization of the basins also began.

The contractor completed a water main adjustment along Woodbine Drive, installed storm sewer along Woodbine Drive, directionally drilled street lighting conduit beneath Orchard Lane, and plowed street lighting conduit along the Hook Drive Extension.

Work Anticipated Next Week
Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are anticipated to take place. Storm sewer installation along Woodbine Drive is scheduled to continue. Stabilization of the detention basins is expected to be completed, and street lighting conduit plowing is planned to continue along the Hook Drive Extension. Excavation and grading for the proposed sidewalk are anticipated to begin along the corridor.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Binder Course Paving and Storm Sewer Work Continuing

Work Completed This Week
The contractor installed inlet filter baskets within the curb along the Hook Drive Extension and continued storm sewer installation along Nicole Lane. Backfilling behind the newly installed curb and gutter progressed throughout the corridor, and the aggregate subgrade was fine graded in preparation for Hot Mix Asphalt binder course paving.

The contractor also connected street lighting conduit above ground in preparation for conduit plowing operations. Both detention basins were dewatered, prime coat was applied, and paving of the Hot Mix Asphalt binder course began along the Hook Drive Extension. Storm sewer installation also began along Woodbine Drive.

Work Anticipated Next Week
Placement of longitudinal joint sealant is expected along the first lift of Hot Mix Asphalt binder course. Tack coat application and additional binder course paving are anticipated to continue throughout the corridor. Fine grading of the detention basins with topsoil is planned, and stabilization work within the basins is projected to be completed. Conduit plowing for the proposed street lighting is scheduled to begin. Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are also anticipated to take place.

Neighborhood Impacts

Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Curb and Gutter Installation Completed

Work Completed This Week
The contractor installed the capping aggregate along the Hook Drive Extension and completed installation of roadway pipe underdrains throughout the corridor. All storm sewer frames located within the curb and gutter sections were installed, and PCC curb and gutter placement was completed along the extension.

Work Anticipated Next Week
Backfilling behind the newly installed curb and gutter is planned to begin along the Hook Drive Extension. Fine grading of the aggregate subgrade is expected to take place in preparation for Hot Mix Asphalt binder course paving. Storm sewer installation along Nicole Lane is anticipated to continue, and Hot Mix Asphalt binder course paving is scheduled to begin along the corridor. Stabilization work within the detention basins is also planned to continue. Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are anticipated to take place.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.