Work Completed This Week The contractor completed topsoil respread along Nicole Lane and Woodbine Drive. The remaining sidewalk gaps along Hook Drive and the sidewalk along the north end of Nicole Lane were prepared and poured. The Lake County Traffic Court sign was reinstalled along Nicole Lane, and mailboxes along Woodbine Drive were returned to their permanent locations. Milling of Nicole Lane and Woodbine Drive was also scheduled to begin on Saturday.
Work Anticipated Next Week Pavement patching and placement of the asphalt leveling binder along Nicole Lane and Woodbine Drive are expected to be completed. The final lift of asphalt is scheduled to be placed on all driveways along Nicole Lane and Woodbine Drive. Permanent seed and blanket installation is anticipated to begin along Nicole Lane and Woodbine Drive, weather permitting.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed Last Week The contractor completed topsoil respread adjacent to the new sidewalk along the Hook Drive Extension. Most of the concrete curb and gutter was poured along Woodbine Drive and Nicole Lane. Directional drilling began for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection, and auguring was completed for the streetlight bases. The contractor also continued grading the aggregate base for roadway widening in preparation for paving and placed the 4-inch Hot Mix Asphalt binder course along the widened sections of Nicole Lane and Woodbine Drive.
The Nicole Lane road closure and detour were removed, and the roadway reopened to traffic early Friday morning, July 3.
Work Anticipated This Week Final grading behind the new curb and gutter is expected to begin, along with placement of topsoil along Nicole Lane and Woodbine Drive. Small sections of concrete curb and gutter along Woodbine Drive, as well as sidewalk along the north side of Nicole Lane and the east Oak Hill driveway apron, are scheduled to be poured. Completion of the remaining concrete light pole bases for the streetlights is anticipated.
Hot Mix Asphalt binder course paving for the driveways is planned to take place, and seed and blanket installation along Nicole Lane and Woodbine Drive is projected to begin. Installation of the permanent traffic signals at the Rollins Road and Nicole Lane/Woodbine Drive intersection is expected to continue.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor completed storm sewer installation along Woodbine Drive and continued removal of curb and gutter along Nicole Lane. Excavation for roadway widening also progressed, along with installation of pipe underdrain and aggregate subbase.
Most of the concrete sidewalk along the Hook Drive Extension was formed and poured during the week. The contractor also removed the existing south entrance to the Lake County Courthouse on Nicole Lane and excavated for the new entrance and parking stalls. As part of the temporary traffic signal work, the Lake County Division of Transportation interconnect along Rollins Road was rerouted.
Work Anticipated Next Week A two-week road closure along Nicole Lane is expected to begin Monday morning. Removal of curb and gutter is anticipated to continue along Nicole Lane and Woodbine Drive. Excavation for roadway widening, along with installation of pipe underdrain and aggregate subbase, is scheduled to continue in both locations.
Completion of the remaining storm sewer installation on Nicole Lane at Rollins Road is planned. Forming and pouring of the remaining sidewalk sections along the Hook Drive Extension are expected to continue. Installation of concrete light pole bases is anticipated to begin, and curb and gutter placement along Nicole Lane and Woodbine Drive is planned.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed Last Week The contractor completed stabilization of both detention basins and continued storm sewer installation along Woodbine Drive. Installation of street lighting conduit along the Hook Drive Extension was completed. The maintenance transfer of the traffic signal at Rollins Road and Nicole Lane/Woodbine Lane was also completed, and installation of temporary traffic signals is underway.
The contractor excavated and graded the proposed sidewalk along the north side of the Hook Drive Extension to subgrade and installed and graded the aggregate base for the future concrete sidewalk.
Work Anticipated This Week Excavation and grading for the proposed sidewalk along the south side of the Hook Drive Extension are expected to begin, along with installation and grading of the aggregate base. Forming for the concrete sidewalk is anticipated to start along the corridor. Installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane is scheduled to continue.
Removal of curb and excavation for roadway widening along Nicole Lane are planned to begin. Installation of concrete light pole bases along the Hook Drive Extension is anticipated, and removal of transite storm sewer along Woodbine Drive is projected to take place.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor completed stabilization of both detention basins and continued storm sewer installation along Woodbine Drive. Installation of street lighting conduit along the Hook Drive Extension was completed. The maintenance transfer of the traffic signal at Rollins Road and Nicole Lane/Woodbine Lane was also completed, and installation of temporary traffic signals is underway.
The contractor excavated and graded the proposed sidewalk along the north side of the Hook Drive Extension to subgrade and installed and graded the aggregate base for the future concrete sidewalk.
Work Anticipated Next Week Excavation and grading for the proposed sidewalk along the south side of the Hook Drive Extension are expected to begin, along with installation and grading of the aggregate base. Forming for the concrete sidewalk is anticipated to start along the corridor. Installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane is scheduled to continue.
Removal of curb and excavation for roadway widening along Nicole Lane are planned to begin. Installation of concrete light pole bases along the Hook Drive Extension is anticipated, and removal of transite storm sewer along Woodbine Drive is planned to take place.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor installed joint sealant along the first lift of Hot Mix Asphalt binder course and finished binder course paving along the Hook Drive Extension. Both detention basins were dewatered due to weekend rain, then fine graded in preparation for final restoration. Stabilization of the basins also began.
The contractor completed a water main adjustment along Woodbine Drive, installed storm sewer along Woodbine Drive, directionally drilled street lighting conduit beneath Orchard Lane, and plowed street lighting conduit along the Hook Drive Extension.
Work Anticipated Next Week Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are anticipated to take place. Storm sewer installation along Woodbine Drive is scheduled to continue. Stabilization of the detention basins is expected to be completed, and street lighting conduit plowing is planned to continue along the Hook Drive Extension. Excavation and grading for the proposed sidewalk are anticipated to begin along the corridor.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor installed inlet filter baskets within the curb along the Hook Drive Extension and continued storm sewer installation along Nicole Lane. Backfilling behind the newly installed curb and gutter progressed throughout the corridor, and the aggregate subgrade was fine graded in preparation for Hot Mix Asphalt binder course paving.
The contractor also connected street lighting conduit above ground in preparation for conduit plowing operations. Both detention basins were dewatered, prime coat was applied, and paving of the Hot Mix Asphalt binder course began along the Hook Drive Extension. Storm sewer installation also began along Woodbine Drive.
Work Anticipated Next Week Placement of longitudinal joint sealant is expected along the first lift of Hot Mix Asphalt binder course. Tack coat application and additional binder course paving are anticipated to continue throughout the corridor. Fine grading of the detention basins with topsoil is planned, and stabilization work within the basins is projected to be completed. Conduit plowing for the proposed street lighting is scheduled to begin. Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are also anticipated to take place.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor installed the capping aggregate along the Hook Drive Extension and completed installation of roadway pipe underdrains throughout the corridor. All storm sewer frames located within the curb and gutter sections were installed, and PCC curb and gutter placement was completed along the extension.
Work Anticipated Next Week Backfilling behind the newly installed curb and gutter is planned to begin along the Hook Drive Extension. Fine grading of the aggregate subgrade is expected to take place in preparation for Hot Mix Asphalt binder course paving. Storm sewer installation along Nicole Lane is anticipated to continue, and Hot Mix Asphalt binder course paving is scheduled to begin along the corridor. Stabilization work within the detention basins is also planned to continue. Maintenance transfer activities and installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are anticipated to take place.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor completed the proof roll and performed necessary subgrade undercuts throughout the Hook Drive Extension corridor. A pressure test was completed on the east section of the 8-inch ductile iron water main. Excavation for directional drilling across Orchard Lane was completed, and two runs of street lighting conduit were installed across the corridor.
Silt fence was installed along Nicole Lane and Woodbine Lane, and the remaining subgrade excavation at the Hook Drive limits near Orchard Lane and Nicole Lane was completed, with excess material hauled off-site. The contractor also installed the 9-inch PGE aggregate subgrade along approximately 95 percent of the corridor and stabilized slopes with permanent seed and blanket. Storm sewer installation began along Nicole Lane. Placement of the 3-inch capping aggregate was also scheduled to begin Saturday.
Work Anticipated Next Week Installation of the 3-inch capping aggregate is expected to be completed along the Hook Drive Extension. Roadway pipe underdrains are anticipated to begin, while installation of street lighting conduit is scheduled to continue throughout the corridor. PCC curb and gutter installation is planned to begin along Hook Drive. Storm sewer work along Nicole Lane is projected to continue, and maintenance transfer activities along with installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are expected to take place.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor completed the water main tap into the existing system along Orchard Lane and installed the remaining 8-inch ductile iron water main in that area. A temporary asphalt patch was placed over the trench.
Work Anticipated Next Week Drying and compaction of the subgrade are expected to continue along the Hook Drive Extension in preparation for proof rolling. Remaining subgrade excavation at the limits near Orchard Lane and Nicole Lane is scheduled to be completed. Installation of conduit and street lighting foundations is planned to begin, along with roadway pipe underdrains and placement of aggregate subgrade. Installation of silt fence along Nicole Lane and Woodbine Lane is anticipated, and storm sewer installation is expected to begin along Nicole Lane.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.