Work Completed This Week The contractor continued topsoil respread along Nicole Lane and Woodbine Drive and completed additional concrete sidewalk placement. Concrete curb and gutter, along with the concrete driveway at the northern Oak Hill entrance from Hook Drive, were poured. The Lake County Courthouse sign was also reinstalled along Nicole Lane.
Directional drilling for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection continued. The contractor prepared and paved Hot Mix Asphalt binder course at the driveways along Nicole Lane and Woodbine Drive. Installation of conduit for the streetlight pole bases was completed, and concrete was poured for all streetlight pole bases and the streetlight foundation along the Hook Drive Extension. Pull tape was also installed through the street lighting conduit in preparation for future cable installation.
Work Anticipated Next Week Topsoil respread along Nicole Lane and Woodbine Drive is expected to continue. Concrete sidewalk placement is anticipated to progress throughout the week. Milling, pavement patching, and placement of the leveling binder course along Nicole Lane and Woodbine Drive are scheduled to be completed.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor implemented the two-week road closure and detour along Nicole Lane on Monday, June 22. The remaining storm sewer installation on Nicole Lane at Rollins Road was completed, while curb and gutter removal, roadway widening, pipe underdrain installation, and aggregate subbase placement continued along Nicole Lane and Woodbine Drive.
Concrete sidewalk construction progressed along the Hook Drive Extension, with additional curb and gutter poured along Nicole Lane and two driveway aprons completed. The contractor also removed the existing handholes and concrete traffic signal bases at the Rollins Road and Nicole Lane/Woodbine Drive intersection and began installing concrete light pole bases for the proposed street lighting.
Work Anticipated Next Week Directional drilling for the proposed traffic signal conduit at the Rollins Road and Nicole Lane/Woodbine Drive intersection is expected to begin. Grading of the aggregate base for roadway widening along Nicole Lane and Woodbine Drive is scheduled to continue in preparation for paving. Completion of curb and gutter placement along Nicole Lane and Woodbine Drive is anticipated, along with the remaining concrete light pole bases.
Pavement patching and Hot Mix Asphalt binder course paving are projected to begin in the widened areas of Nicole Lane and Woodbine Drive, with binder course paving for driveways also planned. Topsoil respread adjacent to the new sidewalk along the Hook Drive Extension is expected to be completed. The Nicole Lane road closure and detour signage are anticipated to be removed on Friday, July 3.
Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.