Storm Sewer Installation Progress

Work Completed This Week
The contractor continued storm sewer installation throughout the Hook Drive Extension corridor and continued hauling of unsuitable material off-site.

Work Anticipated Next Week
Storm sewer installation is anticipated to continue along the Hook Drive Extension throughout the week. Hauling of unsuitable material off-site is anticipated to be completed.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.