Work Completed This Week Construction resumed on the Hook Drive Extension project. The contractor continued storm sewer installation throughout the corridor and began installing water main along the proposed roadway alignment.
Work Anticipated Next Week Water main installation is expected to continue along the Hook Drive Extension corridor. Installation of fire hydrants is planned to begin. Hauling of spoils and grading of the roadway to subgrade is anticipated to take place throughout the site.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.