Work Completed This Week
The contractor performed clearing and grubbing across the project site. Layout for silt fence was completed, and both silt fence and inlet baskets were installed for erosion control. A construction entrance was established at Nicole Lane, and tree stump grinding began throughout the extension corridor.

Work Anticipated Next Week
The contractor plans to continue tree stump grinding across the site and begin topsoil stripping in preparation for future grading and utility work.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.