Aggregate Subgrade and Utility Work Progressing

Work Completed This Week
The contractor completed the proof roll and performed necessary subgrade undercuts throughout the Hook Drive Extension corridor. A pressure test was completed on the east section of the 8-inch ductile iron water main. Excavation for directional drilling across Orchard Lane was completed, and two runs of street lighting conduit were installed across the corridor.

Silt fence was installed along Nicole Lane and Woodbine Lane, and the remaining subgrade excavation at the Hook Drive limits near Orchard Lane and Nicole Lane was completed, with excess material hauled off-site. The contractor also installed the 9-inch PGE aggregate subgrade along approximately 95 percent of the corridor and stabilized slopes with permanent seed and blanket. Storm sewer installation began along Nicole Lane. Placement of the 3-inch capping aggregate was also scheduled to begin Saturday.

Work Anticipated Next Week
Installation of the 3-inch capping aggregate is expected to be completed along the Hook Drive Extension. Roadway pipe underdrains are anticipated to begin, while installation of street lighting conduit is scheduled to continue throughout the corridor. PCC curb and gutter installation is planned to begin along Hook Drive. Storm sewer work along Nicole Lane is projected to continue, and maintenance transfer activities along with installation of temporary traffic signals at Rollins Road and Nicole Lane/Woodbine Lane are expected to take place.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Water Main Work Completed & Subgrade Preparation

Work Completed This Week
The contractor completed the water main tap into the existing system along Orchard Lane and installed the remaining 8-inch ductile iron water main in that area. A temporary asphalt patch was placed over the trench.

Work Anticipated Next Week
Drying and compaction of the subgrade are expected to continue along the Hook Drive Extension in preparation for proof rolling. Remaining subgrade excavation at the limits near Orchard Lane and Nicole Lane is scheduled to be completed. Installation of conduit and street lighting foundations is planned to begin, along with roadway pipe underdrains and placement of aggregate subgrade. Installation of silt fence along Nicole Lane and Woodbine Lane is anticipated, and storm sewer installation is expected to begin along Nicole Lane.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Subgrade Work and Final Grading

Work Completed This Week
The contractor continued earth excavation for the proposed roadway subgrade and final grading throughout the Hook Drive Extension. Excess material was hauled off-site, and placement of topsoil progressed along the slopes on the west half of the corridor.

Work Anticipated Next Week
Earth excavation for the proposed roadway subgrade and final grading are expected to be completed throughout the Hook Drive Extension. Installation of electrical conduit for proposed street lighting is scheduled to begin. Roadway pipe underdrain and 12-inch aggregate subgrade are anticipated to be installed along the corridor. The contractor is expected to complete the hot tap into the existing water main along Orchard Lane.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Subgrade Work Continues

Work Completed This Week
The contractor continued earth excavation for the proposed roadway subgrade throughout the Hook Drive Extension. Work activities were limited due to weather conditions.

Work Anticipated Next Week
Earth excavation for the proposed roadway subgrade is expected to continue. Placement of topsoil on the remaining slopes along the west half of the corridor is scheduled to be completed. Installation of roadway pipe underdrain and aggregate subgrade is anticipated to begin. The contractor is scheduled to complete the hot tap into the existing water main along Orchard Lane.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Subgrade Preparation and Topsoil Placement

Work Completed This Week
The contractor continued earth excavation for the proposed roadway subgrade throughout the Hook Drive Extension. Placement of topsoil was completed on parkway slopes along the east half of the corridor. The remaining topsoil stockpile was also moved outside of the roadway pavement limits.

Work Anticipated Next Week
Earth excavation for the proposed roadway subgrade is expected to continue throughout the Hook Drive Extension. Placement of topsoil is scheduled to be completed on the remaining slopes along the west half of the corridor.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Drainage Features and Utility Testing Completed

Work Completed This Week
The contractor installed temporary perforated risers and manhole restrictor plates at both basin outfalls. Riprap was placed along the Hook Drive Extension, and excess excavation spoils were hauled off-site. Testing of the installed sanitary sewer and water main was also completed.

Work Anticipated Next Week
Hauling of underground excavation spoils and grading of the Hook Drive Extension to subgrade are expected to continue throughout the site. Respreading of topsoil on slopes along Hook Drive is planned to begin.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Storm Sewer and Grading Work

Work Completed This Week
Storm sewer installation continued along the south side of the Hook Drive Extension. The contractor also continued installing water main, with fire hydrants placed along the alignment. Excavation and shaping of slopes progressed throughout the corridor.

Work Anticipated Next Week
Storm sewer installation is expected to be completed along the Hook Drive Extension. Hauling of spoils and grading to subgrade is scheduled to continue across the site. Topsoild respreading is anticipated to begin along the corridor.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Water Main and Hydrant Installation Progressing

Work Completed This Week
Storm sewer installation continued throughout the Hook Drive Extension corridor. The contractor also continued installing water main and began placing fire hydrants along the corridor. Temporary erosion control blanket was installed to stabilize the topsoil stockpile.

Work Anticipated Next Week
Water main installation is expected to continue along the Hook Drive Extension corridor, and installation of the remaining fire hydrants is scheduled to take place. Hauling of spoils and grading of the roadway to subgrade are anticipated to continue throughout the site. Completion of storm sewer installation along the Hook Drive Extension is planned.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Construction Resumes

Work Completed This Week
Construction resumed on the Hook Drive Extension project. The contractor continued storm sewer installation throughout the corridor and began installing water main along the proposed roadway alignment.

Work Anticipated Next Week
Water main installation is expected to continue along the Hook Drive Extension corridor. Installation of fire hydrants is planned to begin. Hauling of spoils and grading of the roadway to subgrade is anticipated to take place throughout the site.

Neighborhood Impacts
Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.

Site Cleanup and Winter Suspension

Work Completed This Week
Storm sewer installation continued throughout the Hook Drive Extension corridor. The contractor also continued hauling unsuitable material off-site. General site cleanup was completed in preparation for suspending work for the winter season.

Work Anticipated Next Week
The project is suspended for the winter due to weather conditions. Work is anticipated to resume in late winter or early spring, as temperatures allow.

Neighborhood Impacts
Project activity will be minimal during the winter suspension. Occasional site access may occur as needed for monitoring or preparation.