Work Completed This Week The contractor continued earth excavation for the proposed roadway subgrade and final grading throughout the Hook Drive Extension. Excess material was hauled off-site, and placement of topsoil progressed along the slopes on the west half of the corridor.
Work Anticipated Next Week Earth excavation for the proposed roadway subgrade and final grading are expected to be completed throughout the Hook Drive Extension. Installation of electrical conduit for proposed street lighting is scheduled to begin. Roadway pipe underdrain and 12-inch aggregate subgrade are anticipated to be installed along the corridor. The contractor is expected to complete the hot tap into the existing water main along Orchard Lane.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor continued earth excavation for the proposed roadway subgrade throughout the Hook Drive Extension. Work activities were limited due to weather conditions.
Work Anticipated Next Week Earth excavation for the proposed roadway subgrade is expected to continue. Placement of topsoil on the remaining slopes along the west half of the corridor is scheduled to be completed. Installation of roadway pipe underdrain and aggregate subgrade is anticipated to begin. The contractor is scheduled to complete the hot tap into the existing water main along Orchard Lane.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor continued earth excavation for the proposed roadway subgrade throughout the Hook Drive Extension. Placement of topsoil was completed on parkway slopes along the east half of the corridor. The remaining topsoil stockpile was also moved outside of the roadway pavement limits.
Work Anticipated Next Week Earth excavation for the proposed roadway subgrade is expected to continue throughout the Hook Drive Extension. Placement of topsoil is scheduled to be completed on the remaining slopes along the west half of the corridor.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week The contractor installed temporary perforated risers and manhole restrictor plates at both basin outfalls. Riprap was placed along the Hook Drive Extension, and excess excavation spoils were hauled off-site. Testing of the installed sanitary sewer and water main was also completed.
Work Anticipated Next Week Hauling of underground excavation spoils and grading of the Hook Drive Extension to subgrade are expected to continue throughout the site. Respreading of topsoil on slopes along Hook Drive is planned to begin.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week Storm sewer installation continued along the south side of the Hook Drive Extension. The contractor also continued installing water main, with fire hydrants placed along the alignment. Excavation and shaping of slopes progressed throughout the corridor.
Work Anticipated Next Week Storm sewer installation is expected to be completed along the Hook Drive Extension. Hauling of spoils and grading to subgrade is scheduled to continue across the site. Topsoild respreading is anticipated to begin along the corridor.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week Storm sewer installation continued throughout the Hook Drive Extension corridor. The contractor also continued installing water main and began placing fire hydrants along the corridor. Temporary erosion control blanket was installed to stabilize the topsoil stockpile.
Work Anticipated Next Week Water main installation is expected to continue along the Hook Drive Extension corridor, and installation of the remaining fire hydrants is scheduled to take place. Hauling of spoils and grading of the roadway to subgrade are anticipated to continue throughout the site. Completion of storm sewer installation along the Hook Drive Extension is planned.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week Construction resumed on the Hook Drive Extension project. The contractor continued storm sewer installation throughout the corridor and began installing water main along the proposed roadway alignment.
Work Anticipated Next Week Water main installation is expected to continue along the Hook Drive Extension corridor. Installation of fire hydrants is planned to begin. Hauling of spoils and grading of the roadway to subgrade is anticipated to take place throughout the site.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week Storm sewer installation continued throughout the Hook Drive Extension corridor. The contractor also continued hauling unsuitable material off-site. General site cleanup was completed in preparation for suspending work for the winter season.
Work Anticipated Next Week The project is suspended for the winter due to weather conditions. Work is anticipated to resume in late winter or early spring, as temperatures allow.
Neighborhood Impacts Project activity will be minimal during the winter suspension. Occasional site access may occur as needed for monitoring or preparation.
Work Completed This Week The contractor continued storm sewer installation throughout the Hook Drive Extension corridor and continued hauling of unsuitable material off-site.
Work Anticipated Next Week Storm sewer installation is anticipated to continue along the Hook Drive Extension throughout the week. Hauling of unsuitable material off-site is anticipated to be completed.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.
Work Completed This Week Storm sewer installation continued throughout the Hook Drive Extension corridor. The contractor also continued earth excavation and embankment placement across the site and hauling of unsuitable material off-site.
Work Anticipated Next Week Storm sewer installation is expected to continue along the Hook Drive Extension throughout the week. Earth excavation and embankment placement are anticipated to progress across the site. Hauling of unsuitable material off-site is planned to be completed. Seeding and blanket placement in both basins are scheduled to begin, along with temporary stabilization of the topsoil stockpiles.
Neighborhood Impacts Construction traffic may be entering and exiting the Hook Drive Extension site at Nicole Lane. Residents and drivers in the area should use caution when traveling near the project entrance. Please watch for construction signage, follow all posted traffic control measures, and visit this website for weekly updates throughout the duration of the project.